Introduction

Nicknamed “Hub City,” Colton, California is home to the Colton Crossing, which was built in 1833 and was one of the busiest at-grade railroad crossings in the United States. Fast forward to the modern-day. Less than two miles south of the original Colton Crossing, on the Santa Ana River bank, are two developing industrial buildings. Strategically placed between the I-10 and I-215 freeways, these buildings offer direct access to San Diego and Los Angeles Counties, and the site is directly adjacent to the Santa Ana River. The proximity to one of the largest rivers in Southern California poses the undeniable need to treat stormwater from the 16-acre site, which will house over 200,000 square feet of warehouse space.

Challenges

Commerce and traffic will dominate this new development’s surface, leaving limited space for large-scale stormwater systems. Furthermore, Colton’s land premiums are a driving force to obtain proven stormwater solutions within a minimal footprint. Tricky soil conditions and the need to address pollutants of concern, such as oil, grease, total suspended solids (TSS), trash, debris, metals, and pathogens, along with meeting the regulations of the Santa Ana Regional Water Quality Board NPDES Permit and County of San Bernardino Water Quality Management Plan, are not easy feats.

 

Solution, Part 1

Thienes Engineering (Engineer of Record) elected to partner with Bio Clean to engineer the site and provide the most efficient solutions. This involves a treatment train of three Bio Clean devices: the Debris Separating Baffle Box (DSBB Separator), UrbanPond® stormwater storage system, and Modular Wetlands® Linear.
The UrbanPond, a traffic-rated underground stormwater storage system, was designed and produced with considerations such as height of cover, live and dead loads, proximity to adjacent structures, and required detention volume. This land-saving precast storage system allows for development above grade while providing stormwater storage below grade. UrbanPond Modules are quick and easy to install, and in this project UrbanPond LinkUP slabs were used, reducing the number of precast modules needed without compromising storage. These LinkUP slabs replace a complete module, roofing the gap when surrounded by four other UrbanPond Modules. Ultimately resulting in a traffic-rated configuration within a minimal surface footprint, saving land, money and time.UrbanPond Treatment Train Graphic

Solution, Part 2

In addition, upstream of the 156 UrbanPond Modules and 37 LinkUP slabs is a hydrodynamic separator, which spearheads this treatment train design. The 5’x’10’ DSBB Separator reduces flow velocity and separates floatables like trash, debris, and oil; and settleable particles such as sediment. This pretreats the stormwater and supports the entire connected systems’ efficiency and long-term maintenance costs. The DSBB Separator is verified by NJCAT, NJDEP certified, and Full Capture approved by the California State Water Resources Control Board.
Downstream of the UrbanPond System are three 10’x20’ Modular Wetland Linear units. The Modular Wetlands provides the highest level of stormwater treatment and is the only* biofiltration product that can be placed downstream of a detention system.
The Modular Wetlands is TAPE GULD approved by Washington Department of Ecology and a CA Full Capture device known for its superior pollutant removal. The Modular Wetlands will treat downstream flows from the UrbanPond for TSS, heavy metals, hydrocarbons, and more. These units were engineered and sized for the required treatment flow rates, working together as a treatment train to address the pollutants of concern, and meet local regulations.

Conclusion

This stormwater project in Colton represents the ability to engineer a creative treatment train system that satisfies local regulations while meeting unique challenges and site constraints. A city with a once historical train crossing now features a cutting-edge stormwater treatment train. Bio Clean is always eager to build partnerships with our clients, delivering efficient treatment and storage configurations, and offering an in-house engineering team to create the best solutions for their sites.

REFERENCES
1. Google Maps Website

Learn More About UrbanPond™

Our local stormwater experts come to you!

UrbanPond™ is a modular precast concrete underground storage system that mimics the function of ponds and open detention basins. Each module is only 8 feet square which minimizes pick weight and crane size requirements. The modular design can be placed under roadways, parking lots and landscape areas in various shapes, sizes, and depths. Request a Lunch & Learn today, and get regionally-focused insight and solutions from a local Bio Clean stormwater expert.

Learn More About the Modular Wetlands System Linear

Our local stormwater experts come to you!

The Modular Wetlands® System Linear (MWS Linear), often considered the most trusted standard for stormwater compliance, uses a smaller footprint yet provides more treatment surface area. It is the only stormwater biofilter using horizontal flow which improves performance and minimizes maintenance. Request a Lunch & Learn today, and get regionally-focused insight and solutions from a local Bio Clean stormwater expert.

Learn More About the DSBB Separator

Our local stormwater experts come to you!

The DSBB Separator (Debris Separating Baffle Box) is an advanced stormwater treatment system utilizing a nonclogging screen technology and hydrodynamic separation to capture pollutants. Request a Lunch & Learn today, and get regionally-focused insight and solutions from a local Bio Clean stormwater expert.